Fields / 33/6-3 S
33/6-3 S
Exploration, appraisalPlugged and abandonedDry
Drilled by Suncor Energy Norge AS with Songa Delta, 17.04.2012 to 24.07.2012 (98 days), to 4 444,0 m in the Lunde Formation.
Water depth332,0 m
Total depth4 444,0 m MD
Vertical depth4 200,0 m TVD
Bottom-hole temperature142 °C
Max inclination38,5°
Rotary table29,0 m
Formation at total depthLunde Formation
RigSonga Delta
Spud17.04.2012
Completed24.07.2012
OperatorSuncor Energy Norge AS
Position61,5941 N, 1,9527 E
Formations
29 tops reported, measured depth in metres.
Temperature
| Reported at total depth | 142 °C |
The wellbore is not in a field, so no field gradient applies.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|
| 34/4-16 S | 5,7 | 3 603,0 | 123 °C | 1,58 | 2021 |
| 34/4-15 A | 5,9 | 3 844,0 | - | - | 2020 |
| 34/4-15 S | 5,9 | 3 570,0 | - | - | 2020 |
| 33/6-2 | 6,3 | 3 950,0 | 137 °C | 1,51 | 1996 |
| 33/6-5 S | 7,1 | 3 515,0 | 116 °C | 1,52 | 2021 |
| 34/4-10 | 7,4 | 2 380,0 | - | 1,54 | 2000 |
| 34/4-10 R | 7,4 | 4 246,0 | 145 °C | 1,83 | 2000 |
| 33/6-1 | 7,8 | 3 900,0 | 103 °C | 1,53 | 1979 |
Casing and formation tests
The casing programme as reported, shallowest first. The test is the leak-off (LOT) or formation integrity (FIT) result as an equivalent mud density.
| String | Casing | Shoe, m | Hole | Hole depth, m | Test, g/cm³ |
|---|
| Conductor | 30" | 439,0 | 36" | 440,0 | - |
| Surface casing | 20" | 1 358,0 | 26" | 1 364,0 | 1,77 LOT |
| Pilot hole | - | 1 363,0 | 9 7/8" | 1 363,0 | - |
| Intermediate | 13 3/8" | 2 484,0 | 17 1/2" | 2 497,0 | 1,84 LOT |
| Intermediate | 9 7/8" | 4 006,0 | 12 1/4" | 4 015,0 | 2,12 LOT |
| Liner | 7" | 4 181,0 | 8 1/2" | 4 184,0 | 2,10 LOT |
| Open hole | - | 4 444,0 | 6" | 4 444,0 | - |
Mud weight
14 measurements, one dot each, 1,00 to 1,99 g/cm³ against measured depth, carbosea obm, magmateq obm, spud mud.