34/10-C-18 B
Development, productionPluggedOil and gas
Drilled by Statoil Petroleum AS with Gullfaks C in Gimle, 27.12.2013 to 27.04.2014 (121 days), to 8 095,0 m.
Water depth216,0 m
Total depth8 095,0 m MD
Vertical depth2 971,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table84,0 m
Formation at total depth-
RigGullfaks C
Spud27.12.2013
Completed27.04.2014
OperatorStatoil Petroleum AS
Position61,2148 N, 2,2744 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Gimle gradient | 40,8 °C/km |
| Estimated at total depth from the gradient | 113 °C |
The gradient is the median of 3 released wells in Gimle with a reported bottom-hole temperature, counted from 4 °C at the sea floor.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 34/10-C-18 same well | 0,0 | 3 280,0 | - | - | 1993 |
| 34/10-C-18 A same well | 0,0 | 8 501,0 | - | - | 2012 |
| 34/10-C-18 C same well | 0,0 | - | - | - | 2026 |
| 34/10-C-1 | 0,0 | 2 717,0 | - | - | 1989 |
| 34/10-C-1 A | 0,0 | 2 595,0 | - | - | 2009 |
| 34/10-C-30 | 0,0 | 3 642,0 | - | - | 1995 |
| 34/10-C-30 A | 0,0 | 2 102,0 | - | - | 2012 |
| 34/10-C-5 | 0,0 | 3 585,0 | - | - | 1990 |
Casing and formation tests
No casing programme is reported for this wellbore.