Fields / Gullfaks / 34/10-C-45 Y2
34/10-C-45 Y2
Development, productionClosedGas
Drilled by Equinor Energy AS with Gullfaks C in Gullfaks, 29.08.2026 to 01.09.2026 (3 days), to 2 725,0 m.
Water depth216,9 m
Total depth2 725,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table84,0 m
Formation at total depth-
RigGullfaks C
Spud29.08.2026
Completed01.09.2026
OperatorEquinor Energy AS
Position61,2149 N, 2,2744 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Gullfaks gradient | 34,7 °C/km |
| Estimated at total depth from the gradient | 88 °C |
The gradient is the median of 18 released wells in Gullfaks with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 34/10-C-45 same well | 0,0 | 2 866,0 | - | - | 2002 |
| 34/10-C-2 | 0,0 | 2 652,0 | - | - | 1990 |
| 34/10-C-24 | 0,0 | 4 575,0 | - | - | 1994 |
| 34/10-C-51 | 0,0 | 6 604,0 | - | - | 2007 |
| 34/10-C-51 A | 0,0 | 8 505,0 | - | - | 2024 |
| 34/10-C-11 | 0,0 | 2 747,0 | - | - | 1992 |
| 34/10-C-11 A | 0,0 | 3 343,0 | - | - | 2018 |
| 34/10-C-41 | 0,0 | 5 352,0 | - | - | 1999 |
Casing and formation tests
No casing programme is reported for this wellbore.