WellplannerNorwegian shelf well data

Fields / Vigdis / 34/7-D-1 AH

34/7-D-1 AH

Development, productionProducing

Drilled by Equinor Energy AS with COSLPromoter in Vigdis, 29.05.2025 to 01.08.2025 (64 days), to 5 735,0 m.

Water depth251,0 m
Total depth5 735,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table25,1 m
Formation at total depth-
RigCOSLPromoter
Spud29.05.2025
Completed01.08.2025
OperatorEquinor Energy AS
Position61,3456 N, 2,0729 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-
Vigdis gradient37,7 °C/km
Estimated at total depth from the gradient210 °C

The gradient is the median of 12 released wells in Vigdis with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
34/7-D-1 H same well0,05 530,0--2003
34/7-D-2 AH0,04 670,0--2008
34/7-D-2 BH0,05 694,0--2021
34/7-D-2 CH0,04 263,0--2025
34/7-D-2 DH0,04 642,0--2025
34/7-D-2 H0,03 247,0--2008
34/7-D-4 AH0,04 400,0--2005
34/7-D-4 H0,04 572,0--2005

Casing and formation tests

No casing programme is reported for this wellbore.

Show on the mapOpen on FactPages ↗