Fields / Ivar Aasen / 16/1-D-4 A
16/1-D-4 A
Development, injectionInjectingWater
Drilled by Aker BP ASA with Maersk Integrator in Ivar Aasen, 05.09.2021 to 13.09.2021 (8 days), to 4 137,0 m.
Water depth112,7 m
Total depth4 137,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table68,2 m
Formation at total depth-
RigMaersk Integrator
Spud05.09.2021
Completed13.09.2021
OperatorAker BP ASA
Position58,9223 N, 2,1981 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Ivar Aasen gradient | 39,1 °C/km |
| Estimated at total depth from the gradient | 158 °C |
The gradient is the median of 6 released wells in Ivar Aasen with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 16/1-D-4 same well | 0,0 | 4 514,0 | - | - | 2016 |
| 16/1-D-8 | 0,0 | 4 222,0 | - | - | 2016 |
| 16/1-D-8 A | 0,0 | 3 655,0 | - | - | 2022 |
| 16/1-D-8 B | 0,0 | 3 472,0 | - | - | 2022 |
| 16/1-D-8 C | 0,0 | 3 898,0 | - | - | 2022 |
| 16/1-D-8 D | 0,0 | - | - | - | - |
| 16/1-D-3 | 0,0 | 3 545,0 | - | - | 2017 |
| 16/1-D-7 | 0,0 | 5 353,0 | - | - | 2018 |
Casing and formation tests
No casing programme is reported for this wellbore.