Fields / 2/1-1

2/1-1

Exploration, wildcatPlugged and abandonedGas shows

Drilled by Conoco Norway Inc. with Ocean Tide, 28.08.1972 to 14.11.1972 (78 days), to 4 178,0 m in the Tyne Group.

Water depth66,0 m
Total depth4 178,0 m MD
Vertical depth-
Bottom-hole temperature126 °C
Max inclination-
Rotary table34,0 m
Formation at total depthTyne Group
RigOcean Tide
Spud28.08.1972
Completed14.11.1972
OperatorConoco Norway Inc.
Position56,7574 N, 3,2052 E

Formations

20 tops reported, measured depth in metres.

GroupsNordland Group, top 100,0 mNordland GpHordaland Group, top 2 207,0 mHordaland GpRogaland Group, top 2 926,0 mRogaland GpShetland Group, top 3 128,0 mShetland GpCromer Knoll Group, top 3 742,0 mCromer Knoll GpNo Data, top 3 886,0 mNo DataFormationsNo Formal Name, top 1 981,0 mNo Formal NameBalder Formation, top 2 926,0 mSele Formation, top 2 937,0 mLista Formation, top 2 944,0 mForties Formation, top 2 981,0 mLista Formation, top 3 013,0 mVidar Formation, top 3 039,0 mLista Formation, top 3 104,0 mEkofisk Formation, top 3 128,0 mTor Formation, top 3 246,0 mTor FmHod Formation, top 3 600,0 mHod FmRødby Formation, top 3 742,0 mTuxen Formation, top 3 755,0 mÅsgard Formation, top 3 775,0 mÅsgard Fm1001 0002 0003 0004 0004 178

Temperature

Reported at total depth126 °C

The wellbore is not in a field, so no field gradient applies.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
2/4-111,64 281,0-1,711973
2/1-54,64 454,0157 °C2,131982
2/4-22 S5,14 889,0173 °C2,162014
2/4-186,9622,0-1,151993
2/4-18 R6,95 310,0199 °C2,041994
2/4-U-337,3103,0--2011
2/4-U-47,4254,0--2010
2/4-U-317,4103,0--2011

Casing and formation tests

The casing programme as reported, shallowest first. The test is the leak-off (LOT) or formation integrity (FIT) result as an equivalent mud density.

StringCasingShoe, mHoleHole depth, mTest, g/cm³
Conductor30"148,036"158,0-
Surface casing20"403,026"415,0-
Intermediate13 3/8"1 154,017 1/2"1 166,0-
Intermediate9 5/8"3 044,012 1/4"3 050,0-
Liner7"3 885,08 1/2"3 886,0-
Open hole-4 178,05 7/8"4 178,0-

Drill-stem tests

Choke in mm, bottom-hole pressure in bar, downhole temperature in °C, oil and gas in Sm³ per day.

TestInterval, mChokePressureTemp.OilGas
13 620,0 - 3 743,0----14 100