2/1-A-22
Development, injectionPlugged and abandonedWater
Drilled by BP Norway Limited U.A. with Gyda in Gyda, 04.09.1991 to 16.10.1991 (42 days), to 4 441,0 m.
Water depth66,0 m
Total depth4 441,0 m MD
Vertical depth4 214,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table56,0 m
Formation at total depth-
RigGyda
Spud04.09.1991
Completed16.10.1991
OperatorBP Norway Limited U.A.
Position56,9048 N, 3,0851 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Gyda gradient | 37,0 °C/km |
| Estimated at total depth from the gradient | 156 °C |
The gradient is the median of 6 released wells in Gyda with a reported bottom-hole temperature, counted from 4 °C at the sea floor.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
Casing and formation tests
No casing programme is reported for this wellbore.