WellplannerNorwegian shelf well data

Fields / Balder / 25/11-8

25/11-8

Exploration, appraisalPlugged and abandonedOil

Drilled by Esso Exploration and Production Norway A/S with Dyvi Alpha in Balder, 08.09.1979 to 16.10.1979 (38 days), to 1 950,0 m in the Ekofisk Formation.

Water depth126,0 m
Total depth1 950,0 m MD
Vertical depth-
Bottom-hole temperature77 °C
Max inclination4,5°
Rotary table25,0 m
Formation at total depthEkofisk Formation
RigDyvi Alpha
Spud08.09.1979
Completed16.10.1979
OperatorEsso Exploration and Production Norway A/S
Position59,1881 N, 2,3611 E

Formations

23 tops reported, measured depth in metres.

GroupsNordland Group, top 150,5 mNordland GpHordaland Group, top 750,0 mHordaland GpRogaland Group, top 1 654,5 mRogaland GpShetland Group, top 1 924,5 mFormationsUtsira Formation, top 585,0 mUtsira FmNo Formal Name, top 725,0 mSkade Formation, top 750,0 mSkade FmNo Formal Name, top 916,0 mSkade Formation, top 948,0 mNo Formal Name, top 968,0 mNo Formal NameSkade Formation, top 1 049,0 mNo Formal Name, top 1 072,0 mNo Formal NameBalder Formation, top 1 654,5 mIntra Balder Fm Ss, top 1 675,0 mBalder Formation, top 1 677,0 mIntra Balder Fm Ss, top 1 693,0 mBalder Formation, top 1 698,0 mSele Formation, top 1 698,5 mLista Formation, top 1 712,0 mHeimdal Formation, top 1 721,5 mHeimdal FmLista Formation, top 1 895,0 mVåle Formation, top 1 915,0 mEkofisk Formation, top 1 924,5 m1505001 0001 5001 954

Temperature

Reported at total depth77 °C
Drill-stem test at 1 767,0 m52 °C
Balder gradient33,9 °C/km
Estimated at total depth from the gradient65 °C

The gradient is the median of 29 released wells in Balder with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
25/11-A-20 AH0,34 356,0--2001
25/11-A-20 H0,35 086,0--2001
25/11-A-22 AH0,33 551,0--2013
25/11-A-22 H0,33 399,0--2013
25/11-A-6 AH0,33 614,0--2001
25/11-A-6 H0,31 807,0--1996
25/11-A-4 AH0,32 122,0--1996
25/11-A-4 BH0,32 923,0--2001

Casing and formation tests

The casing programme as reported, shallowest first. The test is the leak-off (LOT) or formation integrity (FIT) result as an equivalent mud density.

StringCasingShoe, mHoleHole depth, mTest, g/cm³
Conductor30"189,036"189,0-
Surface casing13 3/8"390,017 1/2"402,01,58 LOT
Intermediate9 5/8"1 367,012 1/4"1 383,01,78 LOT
Intermediate7"1 930,08 1/2"1 950,0-

Mud weight

6 measurements, one dot each, 1,00 to 1,15 g/cm³ against measured depth, waterbased.

1,01,11,205001 0001 500402,0 m: 1,04 g/cm³, waterbased689,0 m: 1,07 g/cm³, waterbased1 383,0 m: 1,10 g/cm³, waterbased1 723,0 m: 1,15 g/cm³, waterbased1 751,0 m: 1,13 g/cm³, waterbased1 950,0 m: 1,14 g/cm³, waterbased

Drill-stem tests

Choke in mm, bottom-hole pressure in bar, downhole temperature in °C, oil and gas in Sm³ per day.

TestInterval, mChokePressureTemp.OilGas
11 752,0 - 1 767,015,1-52418-
Show on the mapOpen on FactPages ↗