25/7-12 S
Exploration, wildcatPluggedDry
Drilled by Vår Energi ASA with Deepsea Yantai, 11.12.2023 to 10.01.2024 (30 days), to 2 268,0 m in the Sele Formation.
Water depth127,0 m
Total depth2 268,0 m MD
Vertical depth1 941,4 m TVD
Bottom-hole temperature79 °C
Max inclination48,5°
Rotary table27,3 m
Formation at total depthSele Formation
RigDeepsea Yantai
Spud11.12.2023
Completed10.01.2024
OperatorVår Energi ASA
Position59,2708 N, 2,3151 E
Formations
10 tops reported, measured depth in metres.
Temperature
| Reported at total depth | 79 °C |
The wellbore is not in a field, so no field gradient applies.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
Casing and formation tests
The casing programme as reported, shallowest first. The test is the leak-off (LOT) or formation integrity (FIT) result as an equivalent mud density.
| String | Casing | Shoe, m | Hole | Hole depth, m | Test, g/cm³ |
|---|---|---|---|---|---|
| Conductor | 30" | 241,0 | 36" | 241,0 | - |
| Intermediate | 13 3/8" | 1 044,0 | 17 1/2" | 1 050,0 | - |
| Intermediate | 9 5/8" | 1 765,0 | 12 1/4" | 1 767,0 | 1,67 FIT |
| Open hole | - | 2 267,6 | 8 1/2" | 2 267,6 | 1,70 LOT |
Mud weight
6 measurements, one dot each, 1,20 to 1,92 g/cm³ against measured depth, glydril 1.25, glydril 1.40, rheguard prime obm.