25/7-6
Exploration, appraisalPlugged and abandonedOil shows
Drilled by Norsk Hydro Produksjon AS with Scarabeo 6 in Alvheim, 13.09.2000 to 14.10.2000 (31 days), to 2 250,0 m in the Heimdal Formation.
Water depth124,0 m
Total depth2 250,0 m MD
Vertical depth2 250,0 m TVD
Bottom-hole temperature71 °C
Max inclination1,4°
Rotary table26,0 m
Formation at total depthHeimdal Formation
RigScarabeo 6
Spud13.09.2000
Completed14.10.2000
OperatorNorsk Hydro Produksjon AS
Position59,4875 N, 2,0104 E
Formations
12 tops reported, measured depth in metres.
Temperature
| Reported at total depth | 71 °C |
| Alvheim gradient | 31,8 °C/km |
| Estimated at total depth from the gradient | 71 °C |
The gradient is the median of 6 released wells in Alvheim with a reported bottom-hole temperature, counted from 4 °C at the sea floor.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 25/7-5 | 0,9 | 2 736,0 | 99 °C | 1,45 | 1997 |
| 25/7-A-3 AY1H | 1,3 | 5 330,0 | - | - | 2023 |
| 25/7-A-3 AY2H | 1,3 | 4 944,0 | - | - | 2023 |
| 25/7-A-3 AY3H | 1,3 | 4 973,0 | - | - | 2023 |
| 25/7-A-3 H | 1,3 | 3 265,0 | - | - | 2023 |
| 25/7-A-1 AH | 1,3 | 2 500,0 | - | - | 2023 |
| 25/7-A-1 BY1H | 1,3 | 6 806,0 | - | - | 2023 |
| 25/7-A-1 BY2H | 1,3 | 7 092,0 | - | - | 2023 |
Casing and formation tests
The casing programme as reported, shallowest first. The test is the leak-off (LOT) or formation integrity (FIT) result as an equivalent mud density.
| String | Casing | Shoe, m | Hole | Hole depth, m | Test, g/cm³ |
|---|---|---|---|---|---|
| Conductor | 30" | 223,0 | 36" | 225,0 | 1,60 LOT |
| Surface casing | 13 3/8" | 1 331,0 | 17 1/2" | 1 345,0 | 1,65 LOT |
| Intermediate | 9 5/8" | 1 884,0 | 12 1/4" | 1 891,0 | - |
| Open hole | - | 2 250,0 | 8 1/2" | 2 250,0 | - |
Mud weight
6 measurements, one dot each, 1,20 to 1,50 g/cm³ against measured depth, water based.