WellplannerNorwegian shelf well data

Fields / 30/10-U-2

30/10-U-2

Other, unknownPlugged and abandoned

Drilled by Esso Exploration and Production Norway A/S with Ferder, 09.04.1980 to 30.04.1980 (21 days), to 156,9 m.

Water depth50,5 m
Total depth156,9 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table-
Formation at total depth-
RigFerder
Spud09.04.1980
Completed30.04.1980
OperatorEsso Exploration and Production Norway A/S
Position60,0781 N, 2,1673 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-

The wellbore is not in a field, so no field gradient applies.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
30/10-U-60,1178,5--1980
30/10-U-30,1153,6--1980
30/10-A-10,22 215,0--1984
30/10-A-100,22 759,0--1984
30/10-A-110,22 225,0--1984
30/10-A-120,22 240,0--1984
30/10-A-20,22 170,0--1984
30/10-A-30,22 310,0--1984

Casing and formation tests

No casing programme is reported for this wellbore.

Show on the mapOpen on FactPages ↗