30/11-V-3 H
Development, productionClosedGas
Drilled by Aker BP ASA with Deepsea Stavanger in Munin, 31.08.2025 to 27.09.2026 (392 days), to 6 148,0 m.
Water depth107,0 m
Total depth6 148,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table30,0 m
Formation at total depth-
RigDeepsea Stavanger
Spud31.08.2025
Completed27.09.2026
OperatorAker BP ASA
Position60,1112 N, 2,5923 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Munin gradient | 36,0 °C/km |
| Estimated at total depth from the gradient | 220 °C |
The gradient is the median of 12 released wells in Munin with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 30/11-V-2 H | 0,0 | - | - | - | 2025 |
| 30/11-V-4 H | 0,0 | 3 647,0 | - | - | 2025 |
| 30/11-V-6 H | 0,0 | - | - | - | 2026 |
| 30/11-W-1 H | 0,1 | 6 320,0 | - | - | 2026 |
| 30/11-W-2 AH | 0,1 | - | - | - | 2026 |
| 30/11-W-2 BH | 0,1 | - | - | - | - |
| 30/11-W-2 H | 0,1 | 7 352,0 | - | - | 2025 |
| 30/11-W-3 AH | 0,1 | 4 630,0 | - | - | 2026 |
Casing and formation tests
No casing programme is reported for this wellbore.