Fields / 31/5-U-1
31/5-U-1
Other, soil drillingPlugged and abandoned
Drilled by Norsk Hydro Produksjon AS, 20.09.1987 to 23.09.1987 (3 days), to 70,0 m.
Water depth-
Total depth70,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table2,9 m
Formation at total depth-
Rig-
Spud20.09.1987
Completed23.09.1987
OperatorNorsk Hydro Produksjon AS
Position60,5742 N, 3,6576 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
The wellbore is not in a field, so no field gradient applies.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 31/5-B-3 H | 0,0 | 1 673,0 | - | - | 1990 |
| 31/5-B-2 H | 0,0 | 1 661,0 | - | - | 1990 |
| 31/5-B-5 H | 0,0 | 1 670,0 | - | - | 1990 |
| 31/5-B-4 H | 0,0 | 1 642,0 | - | - | 1990 |
| 31/5-B-6 H | 0,0 | 1 681,0 | - | - | 1989 |
| 31/5-U-2 | 0,0 | 115,0 | - | - | 1987 |
| 31/6-8 | 2,3 | 2 138,0 | 79 °C | 1,35 | 1985 |
| 31/6-8 R | 2,3 | 2 138,0 | 79 °C | 1,20 | 1985 |
Casing and formation tests
No casing programme is reported for this wellbore.