9/2-C-4
Development, productionProducingOil
Drilled by Talisman Energy Norge AS with Mærsk Giant in Yme, 14.02.2009 to 22.11.2009 (281 days), to 4 637,0 m.
Water depth93,0 m
Total depth4 637,0 m MD
Vertical depth3 135,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table45,6 m
Formation at total depth-
RigMærsk Giant
Spud14.02.2009
Completed22.11.2009
OperatorTalisman Energy Norge AS
Position57,8161 N, 4,5355 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Yme gradient | 32,0 °C/km |
| Estimated at total depth from the gradient | 100 °C |
The gradient is the median of 4 released wells in Yme with a reported bottom-hole temperature, counted from 4 °C at the sea floor.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
Casing and formation tests
No casing programme is reported for this wellbore.