PL 124 B
ActiveProduction period, extended
Production licence 124 B was granted 30.09.2024. It is in its production period (extended) and valid to 31.12.2045. Equinor Energy AS is the operator, with four licensees in all.
Granted30.09.2024
Valid to31.12.2045
PhaseProduction period, extended
Licensing round10-B
Area granted76 km²
Area now73 km²
Main areaNorwegian Sea
OperatorEquinor Energy AS
Licensees
| Company | Interest |
|---|---|
| Petoro AS | 36,398 % |
| ConocoPhillips Skandinavia AS | 27,910 % |
| Equinor Energy AS operator | 25,692 % |
| Vår Energi ASA | 10,000 % |
Petoro AS holds the share of the State's Direct Financial Interest (SDFI).
Wellbores drilled in PL 124 B
1 wellbores, 1 of them exploration, newest first.
| Wellbore | Field | Type | Status | Total depth, m | Spud |
|---|---|---|---|---|---|
| 6507/8-12 S | - | Exploration | Plugged and abandoned | 2 511,0 | 17.11.2025 |
Licensees over time
2 sets of licensees since the licence was granted, newest first. A change of company name counts as a change.
Show the history
| From | To | Licensees and interests |
|---|---|---|
| 01.01.2025 | - | Petoro AS ; ConocoPhillips Skandinavia AS ; Equinor Energy AS ; Vår Energi ASA |
| 30.09.2024 | 31.12.2024 | Equinor Energy AS ; ConocoPhillips Skandinavia AS ; Petoro AS ; Vår Energi ASA |