PL 263 G
ActiveInitial period
Production licence 263 G was granted 11.03.2022. It is in its initial period and valid to 11.03.2028. Equinor Energy AS is the operator, with two licensees in all.
Granted11.03.2022
Valid to11.03.2028
PhaseInitial period
Licensing roundTFO2021
Area granted70 km²
Area now70 km²
Main areaNorwegian Sea
OperatorEquinor Energy AS
Licensees
| Company | Interest |
|---|---|
| Equinor Energy AS operator | 51 % |
| Vår Energi ASA | 49 % |
Wellbores
No wellbore in the register is drilled in PL 263 G.
Licensees over time
4 sets of licensees since the licence was granted, newest first. A change of company name counts as a change.
Show the history
| From | To | Licensees and interests |
|---|---|---|
| 30.09.2026 | - | Equinor Energy AS ; Vår Energi ASA |
| 01.11.2022 | 29.09.2026 | Equinor Energy AS ; Pandion Energy AS |
| 30.06.2022 | 31.10.2022 | Equinor Energy AS ; Pandion Energy Norge AS ; Pandion Energy AS |
| 11.03.2022 | 29.06.2022 | Equinor Energy AS ; ONE-Dyas Norge AS ; Pandion Energy AS |