PL 272 C
ActiveProduction period
Production licence 272 C was granted 11.03.2022. It is in its production period and valid to 31.12.2052. Aker BP ASA is the operator, with two licensees in all.
Granted11.03.2022
Valid to31.12.2052
PhaseProduction period
Licensing roundTFO2021
Area granted9 km²
Area now9 km²
Main areaNorth Sea
OperatorAker BP ASA
Licensees
| Company | Interest |
|---|---|
| Aker BP ASA operator | 50 % |
| Equinor Energy AS | 50 % |
Fields
Part of Munin lies in this licence.
Wellbores
No wellbore in the register is drilled in PL 272 C.
Operators over time
| Operator | From | To |
|---|---|---|
| Aker BP ASA | 12.12.2022 | - |
| Equinor Energy AS | 11.03.2022 | 11.12.2022 |