PL 923 B
ActiveInitial period
Production licence 923 B was granted 11.03.2022. It is in its initial period and valid to 11.03.2028. Equinor Energy AS is the operator, with three licensees in all.
Granted11.03.2022
Valid to11.03.2028
PhaseInitial period
Licensing roundTFO2021
Area granted24 km²
Area now24 km²
Main areaNorth Sea
OperatorEquinor Energy AS
Licensees
| Company | Interest |
|---|---|
| Equinor Energy AS operator | 61 % |
| Petoro AS | 20 % |
| Aker BP ASA | 19 % |
Petoro AS holds the share of the State's Direct Financial Interest (SDFI).
Wellbores drilled in PL 923 B
1 wellbores, 1 of them exploration, newest first.
| Wellbore | Field | Type | Status | Total depth, m | Spud |
|---|---|---|---|---|---|
| 31/1-4 | - | Exploration | Plugged | 3 804,0 | 05.11.2024 |
Licensees over time
5 sets of licensees since the licence was granted, newest first. A change of company name counts as a change.
Show the history
| From | To | Licensees and interests |
|---|---|---|
| 30.09.2026 | - | Equinor Energy AS ; Petoro AS ; Aker BP ASA |
| 29.05.2026 | 29.09.2026 | Equinor Energy AS ; Petoro AS |
| 17.12.2025 | 28.05.2026 | Equinor Energy AS ; DNO Norge AS ; Petoro AS |
| 31.05.2023 | 16.12.2025 | Equinor Energy AS ; DNO Norge AS (old) ; Petoro AS |
| 11.03.2022 | 30.05.2023 | Equinor Energy AS ; DNO Norge AS (old) ; Petoro AS ; Wellesley Petroleum AS |