AX0901
Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Gardline Geosurvey Ltd for Aker Exploration AS. Acquired from 13.10.2009 to 27.10.2009.
Planned start01.10.2009
Planned end30.11.2009
Started13.10.2009
Completed27.10.2009
Boat km planned441 km
Boat km done88 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forAker Exploration AS
Responsible companyAker Exploration AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 11 km east to west and 11 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
No vessel is named for this survey in the register.
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 11.10.2009 to 18.10.2009 |
| Boat km in the period | 88 km |
| CDP km in the period | - |
| Boat km so far | 88 km |
| CDP km so far | - |
| Next period planned | 11.10.2009 to 18.10.2009, - |
Notices
15 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 28.10.2009 | Status changed |
| 28.10.2009 | Completion notice |
| 20.10.2009 | Weekly report |
| 14.10.2009 | Status changed |
| 14.10.2009 | Start notice |
| 13.10.2009 | Offshore Directorate letter to the companies |
| 12.10.2009 | Consultation comment, Directorate of Fisheries |
| 09.10.2009 | Change notice |
| 29.09.2009 | Status changed |
| 28.09.2009 | Consultation comment, Institute of Marine Research |
| 28.09.2009 | Offshore Directorate letter to the companies |
| 22.09.2009 | Consultation comment, Directorate of Fisheries |
| 21.09.2009 | Change notice |
| 14.09.2009 | Change notice |
| 11.09.2009 | Status changed |