BPN13301
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for BP Norge AS. Acquired from 05.05.2013 to 07.07.2013.
Planned start28.04.2013
Planned end30.08.2013
Started05.05.2013
Completed07.07.2013
Boat km planned137 km
Boat km done137 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forBP Norge AS
Responsible companyBP Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 11 km east to west and 14 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Ocean Seeker | Acquisition vessel | United Kingdom | 7012179 |
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 26.06.2013 to 04.07.2013 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 243 km |
| CDP km so far | - |
| Next period planned | 04.07.2013 to 13.07.2013, 25 km |
Notices
17 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 30.07.2013 | Weekly report |
| 11.07.2013 | Status changed |
| 11.07.2013 | Completion notice |
| 27.06.2013 | Weekly report |
| 18.06.2013 | Weekly report |
| 06.06.2013 | Weekly report |
| 27.05.2013 | Weekly report |
| 23.05.2013 | Weekly report |
| 13.05.2013 | Weekly report |
| 06.05.2013 | Status changed |
| 06.05.2013 | Start notice |
| 02.05.2013 | Change notice |
| 25.04.2013 | Consultation comment, Institute of Marine Research |
| 25.04.2013 | Offshore Directorate letter to the companies |
| 25.04.2013 | Status changed |
| 24.04.2013 | Consultation comment, Directorate of Fisheries |
| 15.04.2013 | Status changed |