CP21303
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Fugro Norway AS for ConocoPhillips Skandinavia AS. Acquired from 09.08.2021 to 12.08.2021.
Planned start11.07.2021
Planned end15.08.2021
Started09.08.2021
Completed12.08.2021
Boat km planned130 km
Boat km done253 km
Company doing the surveyFugro Norway AS
Acquired forConocoPhillips Skandinavia AS
Responsible companyConocoPhillips Skandinavia AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 5,6 km east to west and 5,6 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 09.08.2021 to 12.08.2021 |
| Boat km in the period | 253 km |
| CDP km in the period | - |
| Boat km so far | 253 km |
| CDP km so far | - |
Notices
16 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 12.08.2021 | Status changed |
| 12.08.2021 | Survey completed |
| 09.08.2021 | Status changed |
| 09.08.2021 | Survey started |
| 02.08.2021 | Change notice, for information |
| 15.07.2021 | Offshore Directorate on a change notice |
| 09.07.2021 | Directorate of Fisheries on a change notice |
| 02.07.2021 | Institute of Marine Research on a change notice |
| 01.07.2021 | Change notice for review |
| 01.07.2021 | Change notice, for information |
| 05.05.2021 | Change notice, for information |
| 03.05.2021 | Status changed |
| 03.05.2021 | Offshore Directorate on the notification |
| 30.04.2021 | Directorate of Fisheries on the notification |
| 29.04.2021 | Institute of Marine Research on the notification |
| 23.04.2021 | Status changed |