WellplannerNorwegian shelf well data

Seismic / 2015 / DN15300

DN15300

Site surveyCompletedNorth Sea

A site survey in the North Sea, acquired by Fugro Survey AS for Det norske oljeselskap AS. Acquired from 08.06.2015 to 13.06.2015.

Planned start01.06.2015
Planned end31.07.2015
Started08.06.2015
Completed13.06.2015
Boat km planned131 km
Boat km done131 km
Company doing the surveyFugro Survey AS
Acquired forDet norske oljeselskap AS
Responsible companyDet norske oljeselskap AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketNo

Survey area

59,12° N59,02° N2,18 to 2,28° E

The outline spans about 6,1 km east to west and 11 km north to south. The outline is the net area as reported, simplified to about 200 m.

Vessels

VesselRoleFlagIMO number
Fugro GalaxyAcquisition vesselBahamas9583445
Fugro MeridianAcquisition vesselBahamas8101331

Licence

The licences the survey is acquired under.

PL 626

Weekly progress

From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.

100 % of the planned boat km
Boat km in the period131 km
CDP km in the period-
Boat km so far267 km
CDP km so far-

Notices

15 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.

DateNotice
15.06.2015Status changed
15.06.2015Weekly report
15.06.2015Completion notice
09.06.2015Status changed
09.06.2015Change notice
09.06.2015Start notice
06.05.2015Offshore Directorate letter to the companies
05.05.2015Consultation comment, Institute of Marine Research
20.04.2015Consultation comment, Directorate of Fisheries
17.04.2015Change notice
09.04.2015Status changed
09.04.2015Offshore Directorate letter to the companies
08.04.2015Consultation comment, Institute of Marine Research
12.03.2015Consultation comment, Directorate of Fisheries
10.03.2015Status changed