DNO25302
Site surveyCompletedNorth Sea
A site survey in the North Sea for DNO Norge AS (old). Acquired from 22.08.2025 to 01.09.2025.
Planned start17.07.2025
Planned end15.10.2025
Started22.08.2025
Completed01.09.2025
Boat km planned400 km
Boat km done400 km
Company doing the surveyDNO Norge AS (old)
Acquired forDNO Norge AS (old)
Responsible companyDNO Norge AS (old)
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketYes
Survey area
The outline spans about 12 km east to west and 12 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Fugro Meridian | Acquisition vessel | Bahamas | 8101331 |
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 30.08.2025 to 01.09.2025 |
| Boat km in the period | 100 km |
| CDP km in the period | - |
| Boat km so far | 400 km |
| CDP km so far | - |
Notices
15 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 01.09.2025 | Status changed |
| 01.09.2025 | Survey completed |
| 29.08.2025 | Period report |
| 25.08.2025 | Institute of Marine Research on a change notice |
| 22.08.2025 | Status changed |
| 22.08.2025 | Survey started |
| 22.08.2025 | Change notice for review |
| 22.08.2025 | Change notice, for information |
| 22.08.2025 | Change notice, for information |
| 09.07.2025 | Status changed |
| 09.07.2025 | Offshore Directorate on the notification |
| 03.07.2025 | Directorate of Fisheries on the notification |
| 18.06.2025 | Institute of Marine Research on the notification |
| 11.06.2025 | Status changed |
| 11.06.2025 | Notification of the survey |