EM0902
4D seabed seismicCompletedNorth Sea
A 4D seabed seismic survey in the North Sea, acquired by Reservoir Exploration Technology ASA for ExxonMobil Exploration and Production Norway AS. Acquired from 14.08.2009 to 20.09.2009.
Planned start14.08.2009
Planned end21.09.2009
Started14.08.2009
Completed20.09.2009
Boat km planned1 030 km
Boat km done342 km
Net area planned, 3D and 4D-
Net area acquired, 3D and 4D-
Company doing the surveyReservoir Exploration Technology ASA
Acquired forExxonMobil Exploration and Production Norway AS
Responsible companyExxonMobil Exploration and Production Norway AS
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 6 000 m long
Offered to the marketNo
Survey area
The outline spans about 7,5 km east to west and 11 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Ocean sea | Acquisition vessel | Bahamas | 9111759 |
| Morning Dawn | Support vessel | United Kingdom | 8701416 |
Licence
The licences the survey is acquired under.
334, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 07.09.2009 to 14.09.2009 |
| Boat km in the period | 113 km |
| CDP km in the period | - |
| Boat km so far | 342 km |
| CDP km so far | - |
| Next period planned | 14.08.2009 to 21.09.2009, 1 054 km |
Notices
22 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 21.09.2009 | Status changed |
| 21.09.2009 | Completion notice |
| 15.09.2009 | Weekly report |
| 15.09.2009 | Change notice |
| 10.09.2009 | Change notice |
| 08.09.2009 | Weekly report |
| 02.09.2009 | Weekly report |
| 28.08.2009 | Change notice |
| 26.08.2009 | Weekly report |
| 19.08.2009 | Weekly report |
| 17.08.2009 | Change notice |
| 13.08.2009 | Status changed |
| 12.08.2009 | Consultation comment, Directorate of Fisheries |
| 12.08.2009 | Offshore Directorate letter to the companies |
| 12.08.2009 | Start notice |
| 21.07.2009 | Change notice |
| 19.07.2009 | Status changed |
| 17.07.2009 | Offshore Directorate letter to the companies |
| 14.07.2009 | Consultation comment, Directorate of Fisheries |
| 09.07.2009 | Change notice |
| 08.07.2009 | Change notice |
| 07.07.2009 | Status changed |