WellplannerNorwegian shelf well data

Seismic / 2014 / EO14301

EO14301

Site surveyCompletedNorth Sea

A site survey in the North Sea, acquired by Fugro Survey AS for E.ON E&P Norge AS. Acquired from 19.09.2014 to 24.09.2014.

Planned start05.09.2014
Planned end20.10.2014
Started19.09.2014
Completed24.09.2014
Boat km planned181 km
Boat km done181 km
Company doing the surveyFugro Survey AS
Acquired forE.ON E&P Norge AS
Responsible companyE.ON E&P Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers, 1 200 m long
Offered to the marketNo

Survey area

58,83° N58,72° N3,33 to 3,98° E

The outline spans about 37 km east to west and 13 km north to south. The outline is the net area as reported, simplified to about 200 m.

Vessels

VesselRoleFlagIMO number
Fugro MeridianAcquisition vesselBahamas8101331
Kommandor CalumAcquisition vesselUnited Kingdom-

Licence

The licences the survey is acquired under.

PL 674

Weekly progress

From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.

100 % of the planned boat km
Boat km in the period181 km
CDP km in the period-
Boat km so far181 km
CDP km so far-

Notices

9 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.

DateNotice
25.09.2014Status changed
25.09.2014Completion notice
18.09.2014Status changed
18.09.2014Start notice
04.09.2014Change notice
29.08.2014Offshore Directorate letter to the companies
28.08.2014Status changed
27.08.2014Consultation comment, Directorate of Fisheries
15.08.2014Status changed
Open on FactPages ↗