EQ19307
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for Equinor Energy AS. Acquired from 21.07.2019 to 07.08.2019.
Planned start18.07.2019
Planned end12.09.2019
Started21.07.2019
Completed07.08.2019
Boat km planned496 km
Boat km done496 km
Net area planned, 3D and 4D16 km²
Net area acquired, 3D and 4D16 km²
Company doing the surveyGardline Geosurvey Ltd
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 6,2 km east to west and 5,6 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 496 km |
| CDP km in the period | - |
| Boat km so far | 1 600 km |
| CDP km so far | - |
Notices
20 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 09.01.2020 | Change notice |
| 07.01.2020 | Change notice |
| 12.08.2019 | Completion notice |
| 07.08.2019 | Status changed |
| 06.08.2019 | Weekly report |
| 29.07.2019 | Weekly report |
| 22.07.2019 | Start notice |
| 21.07.2019 | Status changed |
| 15.07.2019 | Change notice |
| 02.07.2019 | Offshore Directorate letter to the companies |
| 19.06.2019 | Consultation comment, Directorate of Fisheries |
| 19.06.2019 | Change notice |
| 29.05.2019 | Offshore Directorate letter to the companies |
| 24.05.2019 | Consultation comment, Directorate of Fisheries |
| 22.05.2019 | Change notice |
| 16.04.2019 | Status changed |
| 16.04.2019 | Offshore Directorate letter to the companies |
| 03.04.2019 | Consultation comment, Directorate of Fisheries |
| 27.03.2019 | Consultation comment, Institute of Marine Research |
| 25.03.2019 | Status changed |