EQ20301
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for Equinor Energy AS. Acquired from 18.04.2020 to 01.05.2020.
Planned start14.04.2020
Planned end12.05.2020
Started18.04.2020
Completed01.05.2020
Boat km planned350 km
Boat km done350 km
Net area planned, 3D and 4D49 km²
Net area acquired, 3D and 4D49 km²
Company doing the surveyGardline Geosurvey Ltd
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 21 km east to west and 21 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Kommandor | Acquisition vessel | United Kingdom | 8517205 |
Licences
The licences the survey is acquired under.
PL 090693, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 350 km |
| CDP km in the period | - |
| Boat km so far | 602 km |
| CDP km so far | - |
Notices
11 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 04.05.2020 | Completion notice |
| 01.05.2020 | Status changed |
| 27.04.2020 | Weekly report |
| 20.04.2020 | Start notice |
| 18.04.2020 | Status changed |
| 31.03.2020 | Change notice |
| 28.02.2020 | Status changed |
| 28.02.2020 | Offshore Directorate letter to the companies |
| 25.02.2020 | Consultation comment, Directorate of Fisheries |
| 14.02.2020 | Consultation comment, Institute of Marine Research |
| 13.02.2020 | Status changed |