Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Gardline Geosurvey Ltd for Equinor Energy AS. Acquired from 05.07.2021 to 14.07.2021.
Planned start25.06.2021
Planned end11.08.2021
Started05.07.2021
Completed14.07.2021
Boat km planned450 km
Boat km done369 km
Net area planned, 3D and 4D64 km²
Net area acquired, 3D and 4D39 km²
Company doing the surveyGardline Geosurvey Ltd
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 17 km east to west and 14 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 12.07.2021 to 13.07.2021 |
| Boat km in the period | 369 km |
| CDP km in the period | - |
| Boat km so far | 738 km |
| CDP km so far | - |
| Next period planned | 14.07.2021 to -, - |
Notices
11 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 14.07.2021 | Survey completed |
| 13.07.2021 | Status changed |
| 12.07.2021 | Period report |
| 05.07.2021 | Status changed |
| 05.07.2021 | Survey started |
| 28.05.2021 | Status changed |
| 28.05.2021 | Offshore Directorate on the notification |
| 26.05.2021 | Institute of Marine Research on the notification |
| 21.05.2021 | Directorate of Fisheries on the notification |
| 20.05.2021 | Status changed |
| 20.05.2021 | Notification of the survey |