EQ25001
4D seismicCompletedNorwegian Sea
A 4D seismic survey in the Norwegian Sea, acquired by TGS ASA for Equinor Energy AS. Acquired from 01.05.2025 to 15.09.2025.
Planned start01.05.2025
Planned end25.09.2025
Started01.05.2025
Completed15.09.2025
Boat km planned2 175 km
Boat km done1 517 km
Net area planned, 3D and 4D323 km²
Net area acquired, 3D and 4D297 km²
Company doing the surveyTGS ASA
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 3 675 m long
Offered to the marketNo
Survey area
The outline spans about 18 km east to west and 22 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 21.06.2025 to 15.09.2025 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 419 km |
| CDP km so far | - |
Notices
26 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 15.09.2025 | Status changed |
| 15.09.2025 | Survey completed |
| 09.09.2025 | Status changed |
| 09.09.2025 | Period report |
| 09.09.2025 | Survey resumed |
| 05.09.2025 | Institute of Marine Research on a change notice |
| 04.09.2025 | Change notice for review |
| 04.09.2025 | Change notice, for information |
| 20.06.2025 | Status changed |
| 20.06.2025 | Survey paused |
| 10.06.2025 | Period report |
| 26.05.2025 | Period report |
| 12.05.2025 | Period report |
| 01.05.2025 | Status changed |
| 01.05.2025 | Survey started |
| 01.05.2025 | Change notice, for information |
| 19.03.2025 | Change notice, for information |
| 19.03.2025 | Change notice, for information |
| 19.03.2025 | Change notice, for information |
| 19.03.2025 | Change notice, for information |
| 24.02.2025 | Status changed |
| 24.02.2025 | Offshore Directorate on the notification |
| 20.02.2025 | Directorate of Fisheries on the notification |
| 29.01.2025 | Institute of Marine Research on the notification |
| 16.01.2025 | Status changed |
| 16.01.2025 | Notification of the survey |