EQ25300
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Limited for Equinor Energy AS. Acquired from 30.04.2025 to 13.05.2025.
Planned start20.04.2025
Planned end10.06.2025
Started30.04.2025
Completed13.05.2025
Boat km planned250 km
Boat km done344 km
Net area planned, 3D and 4D6 km²
Net area acquired, 3D and 4D4 km²
Company doing the surveyGardline Limited
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 20 km east to west and 22 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Ocean Resolution | Acquisition vessel | United Kingdom | 9779446 |
Licences
The licences the survey is acquired under.
PL 054856, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 05.05.2025 to 13.05.2025 |
| Boat km in the period | 292 km |
| CDP km in the period | - |
| Boat km so far | 344 km |
| CDP km so far | - |
Notices
13 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 13.05.2025 | Status changed |
| 13.05.2025 | Survey completed |
| 05.05.2025 | Period report |
| 30.04.2025 | Status changed |
| 30.04.2025 | Survey started |
| 30.04.2025 | Change notice, for information |
| 02.04.2025 | Change notice, for information |
| 26.03.2025 | Change notice, for information |
| 14.02.2025 | Status changed |
| 14.02.2025 | Offshore Directorate on the notification |
| 13.02.2025 | Directorate of Fisheries on the notification |
| 06.02.2025 | Institute of Marine Research on the notification |
| 31.01.2025 | Status changed |