EQ25309
Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Gardline Limited for Equinor Energy AS. Acquired from 16.04.2025 to 13.06.2025.
Planned start15.04.2025
Planned end10.07.2025
Started16.04.2025
Completed13.06.2025
Boat km planned600 km
Boat km done465 km
Company doing the surveyGardline Limited
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 22 km east to west and 24 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 16.05.2025 to 13.06.2025 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 560 km |
| CDP km so far | - |
Notices
19 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 13.06.2025 | Status changed |
| 13.06.2025 | Survey completed |
| 05.06.2025 | Directorate of Fisheries on a change notice |
| 05.06.2025 | Offshore Directorate on a change notice |
| 30.05.2025 | Institute of Marine Research on a change notice |
| 22.05.2025 | Change notice for review |
| 15.05.2025 | Status changed |
| 15.05.2025 | Period report |
| 15.05.2025 | Survey paused |
| 09.05.2025 | Period report |
| 30.04.2025 | Period report |
| 16.04.2025 | Status changed |
| 16.04.2025 | Survey started |
| 26.03.2025 | Change notice, for information |
| 06.03.2025 | Status changed |
| 06.03.2025 | Offshore Directorate on the notification |
| 05.03.2025 | Institute of Marine Research on the notification |
| 03.03.2025 | Directorate of Fisheries on the notification |
| 27.02.2025 | Status changed |