WellplannerNorwegian shelf well data

Seismic / 2026 / EQ26042

EQ26042

Site surveyCompletedBarents Sea

A site survey in the Barents Sea, acquired by Gardline Limited for Equinor Energy AS. Acquired from 05.07.2026 to 25.07.2026.

Planned start30.06.2026
Planned end31.08.2026
Started05.07.2026
Completed25.07.2026
Boat km planned500 km
Boat km done284 km
Net area planned, 3D and 4D9 km²
Net area acquired, 3D and 4D10 km²
Company doing the surveyGardline Limited
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 1 200 m long
Offered to the marketNo

Survey area

74,03° N73,84° N24,65 to 25,41° E

The outline spans about 23 km east to west and 21 km north to south. The outline is the net area as reported, simplified to about 200 m.

Vessel

VesselRoleFlagIMO number
Ocean ResolutionAcquisition vesselUnited Kingdom9779446

Licence

The licences the survey is acquired under.

862, exploration licence

Weekly progress

From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.

55 % of the planned boat km
Latest report covers20.07.2026 to 25.07.2026
Boat km in the period185 km
CDP km in the period-
Boat km so far274 km
CDP km so far-

Notices

14 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.

DateNotice
25.07.2026Status changed
25.07.2026Survey completed
21.07.2026Period report
14.07.2026Period report
05.07.2026Status changed
05.07.2026Survey started
20.06.2026Change notice, for information
20.06.2026Change notice, for information
15.05.2026Status changed
15.05.2026Offshore Directorate on the notification
12.05.2026Directorate of Fisheries on the notification
11.05.2026Institute of Marine Research on the notification
08.05.2026Status changed
08.05.2026Notification of the survey