WellplannerNorwegian shelf well data

Seismic / 2026 / EQ26049

EQ26049

Site surveyCompletedBarents Sea

A site survey in the Barents Sea, acquired by Gardline Limited for Equinor Energy AS. Acquired from 14.07.2026 to 30.07.2026.

Planned start07.07.2026
Planned end15.09.2026
Started14.07.2026
Completed30.07.2026
Boat km planned300 km
Boat km done234 km
Net area planned, 3D and 4D5 km²
Net area acquired, 3D and 4D5 km²
Company doing the surveyGardline Limited
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 1 200 m long
Offered to the marketNo

Survey area

73,51° N73,33° N23,78 to 24,40° E

The outline spans about 20 km east to west and 21 km north to south. The outline is the net area as reported, simplified to about 200 m.

Vessel

VesselRoleFlagIMO number
Ocean ResolutionAcquisition vesselUnited Kingdom9779446

Licences

The licences the survey is acquired under.

PL 537862, exploration licence

Weekly progress

From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.

66 % of the planned boat km
Latest report covers27.07.2026 to 30.07.2026
Boat km in the period54 km
CDP km in the period-
Boat km so far198 km
CDP km so far-

Notices

14 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.

DateNotice
30.07.2026Status changed
30.07.2026Survey completed
29.07.2026Change notice, for information
27.07.2026Period report
21.07.2026Period report
14.07.2026Status changed
14.07.2026Survey started
20.06.2026Change notice, for information
11.06.2026Status changed
11.06.2026Offshore Directorate on the notification
10.06.2026Directorate of Fisheries on the notification
08.06.2026Institute of Marine Research on the notification
01.06.2026Status changed
01.06.2026Notification of the survey
Open on FactPages ↗