IPN1101
3D seismicCompletedNorth Sea
A 3D seismic survey in the North Sea, acquired by Fugro-Geoteam AS for Idemitsu Petroleum Norge AS. Acquired from 15.07.2011 to 04.08.2011.
Planned start09.07.2011
Planned end31.08.2011
Started15.07.2011
Completed04.08.2011
Boat km planned908 km
Boat km done1 284 km
Net area planned, 3D and 4D-
Net area acquired, 3D and 4D-
Company doing the surveyFugro-Geoteam AS
Acquired forIdemitsu Petroleum Norge AS
Responsible companyIdemitsu Petroleum Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 21 km east to west and 52 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 01.08.2011 to 04.08.2011 |
| Boat km in the period | 908 km |
| CDP km in the period | - |
| Boat km so far | 1 284 km |
| CDP km so far | - |
| Next period planned | 05.08.2011 to 31.08.2011, - |
Notices
16 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 04.01.2012 | Completion notice |
| 09.11.2011 | Status changed |
| 16.09.2011 | Status changed |
| 05.08.2011 | Weekly report |
| 04.08.2011 | Status changed |
| 01.08.2011 | Weekly report |
| 28.07.2011 | Change notice |
| 22.07.2011 | Weekly report |
| 14.07.2011 | Status changed |
| 12.07.2011 | Start notice |
| 01.07.2011 | Status changed |
| 01.07.2011 | Offshore Directorate letter to the companies |
| 30.06.2011 | Consultation comment, Institute of Marine Research |
| 30.06.2011 | Consultation comment, Directorate of Fisheries |
| 27.06.2011 | Change notice |
| 01.06.2011 | Status changed |