LN12502
Soil surveyCompletedNorth Sea
A soil survey in the North Sea, acquired by Fugro Survey AS for Lundin Norway AS. Acquired from 11.05.2012 to 18.05.2012.
Planned start09.03.2012
Planned end31.05.2012
Started11.05.2012
Completed18.05.2012
Boat km planned117 km
Boat km done26 km
Company doing the surveyFugro Survey AS
Acquired forLundin Norway AS
Responsible companyLundin Norway AS
Legal basisPetroleum regulations
Offered to the marketNo
Survey area
The outline spans about 2,0 km east to west and 37 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Birkeland | Acquisition vessel | Norway | 9281645 |
| Kommandor Calum | Acquisition vessel | United Kingdom | - |
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 12.05.2012 to 18.05.2012 |
| Boat km in the period | 26 km |
| CDP km in the period | - |
| Boat km so far | 26 km |
| CDP km so far | - |
| Next period planned | 18.05.2012 to 25.05.2012, 91 km |
Notices
12 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 21.05.2012 | Status changed |
| 21.05.2012 | Start notice |
| 21.05.2012 | Completion notice |
| 21.05.2012 | Weekly report |
| 18.05.2012 | Status changed |
| 09.05.2012 | Offshore Directorate letter to the companies |
| 07.05.2012 | Consultation comment, Directorate of Fisheries |
| 07.05.2012 | Change notice |
| 30.03.2012 | Offshore Directorate letter to the companies |
| 30.03.2012 | Status changed |
| 29.03.2012 | Consultation comment, Directorate of Fisheries |
| 08.03.2012 | Status changed |