LN20300
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Fugro Norway AS for Lundin Norway AS. Acquired from 31.08.2020 to 04.09.2020.
Planned start25.08.2020
Planned end31.10.2020
Started31.08.2020
Completed04.09.2020
Boat km planned138 km
Boat km done138 km
Net area planned, 3D and 4D21 km²
Net area acquired, 3D and 4D21 km²
Company doing the surveyFugro Norway AS
Acquired forLundin Norway AS
Responsible companyLundin Norway AS
Legal basisPetroleum regulations
SourceSeismic, 6 sources
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 6,9 km east to west and 6,1 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 138 km |
| CDP km in the period | - |
| Boat km so far | 138 km |
| CDP km so far | - |
Notices
12 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 04.09.2020 | Status changed |
| 04.09.2020 | Completion notice |
| 01.09.2020 | Start notice |
| 31.08.2020 | Status changed |
| 31.08.2020 | Status changed |
| 31.08.2020 | Offshore Directorate letter to the companies |
| 28.08.2020 | Consultation comment, Directorate of Fisheries |
| 25.08.2020 | Consultation comment, Institute of Marine Research |
| 21.08.2020 | Change notice |
| 17.08.2020 | Change notice |
| 30.07.2020 | Status changed |
| 30.07.2020 | Consultation comment, Institute of Marine Research |