Site surveyCompletedNorwegian Sea

A site survey in the Norwegian Sea, acquired by Fugro Survey AS for Neptune Energy Norge AS. Acquired from 01.06.2020 to 10.06.2020.

Planned start20.05.2020
Planned end20.06.2020
Started01.06.2020
Completed10.06.2020
Boat km planned232 km
Boat km done232 km
Net area planned, 3D and 4D4 km²
Net area acquired, 3D and 4D4 km²
Company doing the surveyFugro Survey AS
Acquired forNeptune Energy Norge AS
Responsible companyNeptune Energy Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo

Survey area

63,76° N63,71° N6,39 to 6,61° E

The outline spans about 11 km east to west and 5,3 km north to south. The outline is the net area as reported, simplified to about 200 m.

Vessel

VesselRoleFlagIMO number
Fugro MeridianAcquisition vesselBahamas8101331

Licence

The licences the survey is acquired under.

PL 936

Weekly progress

From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.

100 % of the planned boat km
Boat km in the period232 km
CDP km in the period-
Boat km so far464 km
CDP km so far-

Notices

10 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.

DateNotice
11.06.2020Completion notice
10.06.2020Status changed
09.06.2020Weekly report
02.06.2020Start notice
01.06.2020Status changed
24.04.2020Status changed
24.04.2020Consultation comment, Institute of Marine Research
24.04.2020Offshore Directorate letter to the companies
16.04.2020Consultation comment, Directorate of Fisheries
14.04.2020Status changed
Open on FactPages ↗