SH1001
3D seismicCompletedNorwegian Sea
A 3D seismic survey in the Norwegian Sea, acquired by CGGVeritas Services (Norway) AS for A/S Norske Shell. Acquired from 12.07.2010 to 10.08.2010.
Planned start03.06.2010
Planned end31.08.2010
Started12.07.2010
Completed10.08.2010
Boat km planned2 097 km
Boat km done2 586 km
Net area planned, 3D and 4D-
Net area acquired, 3D and 4D-
Company doing the surveyCGGVeritas Services (Norway) AS
Acquired forA/S Norske Shell
Responsible companyA/S Norske Shell
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 6 000 m long
Offered to the marketYes
Survey area
The outline spans about 45 km east to west and 72 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Tuna | Acquisition vessel | France | 9194115 |
Licence
The licences the survey is acquired under.
378, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 09.08.2010 to 10.08.2010 |
| Boat km in the period | 100 km |
| CDP km in the period | - |
| Boat km so far | 2 586 km |
| CDP km so far | - |
| Next period planned | 06.06.2010 to 10.08.2010, 2 427 km |
Notices
19 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 11.08.2010 | Status changed |
| 11.08.2010 | Weekly report |
| 11.08.2010 | Completion notice |
| 09.08.2010 | Weekly report |
| 02.08.2010 | Weekly report |
| 26.07.2010 | Weekly report |
| 19.07.2010 | Weekly report |
| 12.07.2010 | Start notice |
| 12.07.2010 | Change notice |
| 07.06.2010 | Weekly report |
| 02.06.2010 | Status changed |
| 02.06.2010 | Start notice |
| 26.05.2010 | Change notice |
| 30.03.2010 | Consultation comment, Directorate of Fisheries |
| 30.03.2010 | Offshore Directorate letter to the companies |
| 30.03.2010 | Status changed |
| 25.03.2010 | Change notice |
| 19.03.2010 | Consultation comment, Institute of Marine Research |
| 05.03.2010 | Status changed |