ST10015
4D seismicCompletedNorth Sea
A 4D seismic survey in the North Sea, acquired by WesternGeco AS for Statoil Petroleum AS. Acquired from 15.07.2010 to 24.08.2010.
Planned start08.07.2010
Planned end02.09.2010
Started15.07.2010
Completed24.08.2010
Boat km planned32 200 km
Boat km done1 083 km
Net area planned, 3D and 4D-
Net area acquired, 3D and 4D-
Company doing the surveyWesternGeco AS
Acquired forStatoil Petroleum AS
Responsible companyStatoil Petroleum AS
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 5 000 m long
Offered to the marketYes
Survey area
The outline spans about 29 km east to west and 35 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Western Monarch | Acquisition vessel | - | 9010149 |
| Faxaborg | Support vessel | Vanuatu | 6810471 |
| Geco Topaz | Other vessel | Panama | 9048689 |
| Shalom II | Support vessel | Panama | 7211892 |
Licence
The licences the survey is acquired under.
363, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 16.08.2010 to 22.08.2010 |
| Boat km in the period | 6 km |
| CDP km in the period | - |
| Boat km so far | 1 083 km |
| CDP km so far | - |
| Next period planned | 23.08.2010 to 25.08.2010, 711 km |
Notices
19 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 25.08.2010 | Status changed |
| 25.08.2010 | Weekly report |
| 25.08.2010 | Completion notice |
| 16.08.2010 | Weekly report |
| 09.08.2010 | Weekly report |
| 05.08.2010 | Change notice |
| 03.08.2010 | Weekly report |
| 27.07.2010 | Weekly report |
| 19.07.2010 | Weekly report |
| 16.07.2010 | Status changed |
| 16.07.2010 | Start notice |
| 29.06.2010 | Offshore Directorate letter to the companies |
| 25.06.2010 | Consultation comment, Directorate of Fisheries |
| 24.06.2010 | Change notice |
| 07.06.2010 | Consultation comment, Institute of Marine Research |
| 07.06.2010 | Offshore Directorate letter to the companies |
| 07.06.2010 | Status changed |
| 19.05.2010 | Consultation comment, Directorate of Fisheries |
| 18.05.2010 | Status changed |