ST11311
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for Statoil ASA. Acquired from 05.11.2011 to 01.12.2011.
Planned start07.12.2011
Planned end20.12.2011
Started05.11.2011
Completed01.12.2011
Boat km planned266 km
Boat km done230 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forStatoil ASA
Responsible companyStatoil ASA
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketYes
Survey area
The outline spans about 17 km east to west and 17 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 21.11.2011 to 27.11.2011 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 230 km |
| CDP km so far | - |
| Next period planned | 28.11.2011 to 04.12.2011, 67 km |
Notices
19 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 02.12.2011 | Status changed |
| 02.12.2011 | Completion notice |
| 02.12.2011 | Start notice |
| 28.11.2011 | Weekly report |
| 24.11.2011 | Status changed |
| 23.11.2011 | Change notice |
| 21.11.2011 | Weekly report |
| 14.11.2011 | Change notice |
| 14.11.2011 | Weekly report |
| 07.11.2011 | Status changed |
| 07.10.2011 | Change notice |
| 21.09.2011 | Offshore Directorate letter to the companies |
| 19.09.2011 | Consultation comment, Directorate of Fisheries |
| 15.09.2011 | Change notice |
| 02.09.2011 | Status changed |
| 02.09.2011 | Offshore Directorate letter to the companies |
| 30.08.2011 | Consultation comment, Institute of Marine Research |
| 30.08.2011 | Consultation comment, Directorate of Fisheries |
| 15.08.2011 | Status changed |