ST15305
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for Statoil ASA. Acquired from 01.05.2015 to 12.06.2015.
Planned start12.03.2015
Planned end19.06.2015
Started01.05.2015
Completed12.06.2015
Boat km planned477 km
Boat km done477 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forStatoil ASA
Responsible companyStatoil ASA
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 11 km east to west and 11 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 477 km |
| CDP km in the period | - |
| Boat km so far | 832 km |
| CDP km so far | - |
Notices
19 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 02.12.2015 | Change notice |
| 15.06.2015 | Status changed |
| 15.06.2015 | Completion notice |
| 09.06.2015 | Weekly report |
| 01.06.2015 | Weekly report |
| 01.06.2015 | Weekly report |
| 29.05.2015 | Consultation comment, Institute of Marine Research |
| 29.05.2015 | Consultation comment, Directorate of Fisheries |
| 28.05.2015 | Change notice |
| 19.05.2015 | Weekly report |
| 11.05.2015 | Weekly report |
| 04.05.2015 | Weekly report |
| 30.04.2015 | Status changed |
| 30.04.2015 | Start notice |
| 26.03.2015 | Status changed |
| 26.03.2015 | Consultation comment, Institute of Marine Research |
| 26.03.2015 | Offshore Directorate letter to the companies |
| 12.02.2015 | Consultation comment, Directorate of Fisheries |
| 10.02.2015 | Status changed |