Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Gardline Geosurvey Ltd for Statoil Petroleum AS. Acquired from 26.04.2016 to 27.05.2016.
Planned start08.04.2016
Planned end19.06.2016
Started26.04.2016
Completed27.05.2016
Boat km planned349 km
Boat km done349 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forStatoil Petroleum AS
Responsible companyStatoil Petroleum AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 13 km east to west and 13 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
No vessel is named for this survey in the register.
Licences
The licences the survey is acquired under.
PL 128 D534, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 349 km |
| CDP km in the period | - |
| Boat km so far | 640 km |
| CDP km so far | - |
Notices
15 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 30.05.2016 | Status changed |
| 27.05.2016 | Completion notice |
| 24.05.2016 | Weekly report |
| 18.05.2016 | Weekly report |
| 09.05.2016 | Weekly report |
| 27.04.2016 | Status changed |
| 27.04.2016 | Start notice |
| 08.04.2016 | Status changed |
| 21.03.2016 | Status changed |
| 21.03.2016 | Offshore Directorate letter to the companies |
| 17.03.2016 | Consultation comment, Directorate of Fisheries |
| 14.03.2016 | Consultation comment, Institute of Marine Research |
| 10.03.2016 | Change notice |
| 09.03.2016 | Consultation comment, Directorate of Fisheries |
| 29.02.2016 | Status changed |