ST18317
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for Equinor Energy AS. Acquired from 25.07.2018 to 31.08.2018.
Planned start04.06.2018
Planned end12.09.2018
Started25.07.2018
Completed31.08.2018
Boat km planned1 107 km
Boat km done1 107 km
Net area planned, 3D and 4D27 km²
Net area acquired, 3D and 4D27 km²
Company doing the surveyGardline Geosurvey Ltd
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 8,5 km east to west and 8,4 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 1 107 km |
| CDP km in the period | - |
| Boat km so far | 2 880 km |
| CDP km so far | - |
Notices
16 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 03.09.2018 | Completion notice |
| 31.08.2018 | Status changed |
| 28.08.2018 | Weekly report |
| 21.08.2018 | Weekly report |
| 14.08.2018 | Weekly report |
| 06.08.2018 | Weekly report |
| 30.07.2018 | Weekly report |
| 26.07.2018 | Change notice |
| 26.07.2018 | Start notice |
| 25.07.2018 | Status changed |
| 13.03.2018 | Status changed |
| 13.03.2018 | Offshore Directorate letter to the companies |
| 05.03.2018 | Consultation comment, Institute of Marine Research |
| 05.03.2018 | Consultation comment, Directorate of Fisheries |
| 01.03.2018 | Change notice |
| 28.02.2018 | Status changed |