SUN11NO01
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Gardline Geosurvey Ltd for Suncor Energy Norge AS. Acquired from 10.05.2011 to 18.05.2011.
Planned start09.05.2011
Planned end20.06.2011
Started10.05.2011
Completed18.05.2011
Boat km planned346 km
Boat km done246 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forSuncor Energy Norge AS
Responsible companySuncor Energy Norge AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketYes
Survey area
The outline spans about 15 km east to west and 12 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 09.05.2011 to 15.05.2011 |
| Boat km in the period | 246 km |
| CDP km in the period | - |
| Boat km so far | 246 km |
| CDP km so far | - |
| Next period planned | 16.05.2011 to 22.05.2011, 120 km |
Notices
13 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 19.05.2011 | Status changed |
| 19.05.2011 | Completion notice |
| 16.05.2011 | Weekly report |
| 10.05.2011 | Status changed |
| 10.05.2011 | Start notice |
| 03.05.2011 | Status changed |
| 03.05.2011 | Offshore Directorate letter to the companies |
| 02.05.2011 | Consultation comment, Institute of Marine Research |
| 29.04.2011 | Consultation comment, Directorate of Fisheries |
| 28.04.2011 | Change notice |
| 26.04.2011 | Change notice |
| 31.03.2011 | Consultation comment, Directorate of Fisheries |
| 29.03.2011 | Status changed |