TEPN-13-2
Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Gardline Geosurvey Ltd for Total E&P Norge AS. Acquired from 04.04.2013 to 21.07.2013.
Planned start03.04.2013
Planned end25.07.2013
Started04.04.2013
Completed21.07.2013
Boat km planned500 km
Boat km done500 km
Company doing the surveyGardline Geosurvey Ltd
Acquired forTotal E&P Norge AS
Responsible companyTotal E&P Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers, 1 500 m long
Offered to the marketNo
Survey area
The outline spans about 11 km east to west and 13 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Kommandor | Acquisition vessel | United Kingdom | 8517205 |
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 500 km |
| CDP km in the period | - |
| Boat km so far | 500 km |
| CDP km so far | - |
Notices
15 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 30.07.2013 | Consultation comment, Directorate of Fisheries |
| 22.07.2013 | Status changed |
| 22.07.2013 | Change notice |
| 22.07.2013 | Change notice |
| 22.07.2013 | Completion notice |
| 04.06.2013 | Change notice |
| 30.05.2013 | Change notice |
| 11.04.2013 | Change notice |
| 05.04.2013 | Start notice |
| 04.04.2013 | Status changed |
| 04.04.2013 | Status changed |
| 03.04.2013 | Consultation comment, Directorate of Fisheries |
| 03.04.2013 | Offshore Directorate letter to the companies |
| 02.04.2013 | Consultation comment, Institute of Marine Research |
| 02.04.2013 | Status changed |