VE26003
4D seismicCompletedNorth Sea
A 4D seismic survey in the North Sea, acquired by TGS ASA for Vår Energi ASA. Acquired from 30.07.2026 to 04.09.2026.
Planned start31.07.2026
Planned end25.09.2026
Started30.07.2026
Completed04.09.2026
Boat km planned-
Boat km done2 955 km
Net area planned, 3D and 4D-
Net area acquired, 3D and 4D738 km²
Company doing the surveyTGS ASA
Acquired forVår Energi ASA
Responsible companyVår Energi ASA
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 2 625 m long
Offered to the marketNo
Survey area
The outline spans about 50 km east to west and 65 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 30.07.2026 to 04.09.2026 |
| Boat km in the period | 2 954 km |
| CDP km in the period | - |
| Boat km so far | 2 955 km |
| CDP km so far | - |
Notices
21 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 04.09.2026 | Status changed |
| 04.09.2026 | Survey completed |
| 31.07.2026 | Change notice, for information |
| 31.07.2026 | Change notice, for information |
| 30.07.2026 | Status changed |
| 30.07.2026 | Survey started |
| 22.07.2026 | Offshore Directorate on a change notice |
| 20.07.2026 | Directorate of Fisheries on a change notice |
| 16.07.2026 | Institute of Marine Research on a change notice |
| 14.07.2026 | Change notice for review |
| 14.07.2026 | Change notice, for information |
| 14.07.2026 | Change notice, for information |
| 03.06.2026 | Change notice, for information |
| 28.05.2026 | Change notice, for information |
| 28.05.2026 | Change notice, for information |
| 27.05.2026 | Status changed |
| 27.05.2026 | Offshore Directorate on the notification |
| 26.05.2026 | Directorate of Fisheries on the notification |
| 20.05.2026 | Institute of Marine Research on the notification |
| 19.05.2026 | Status changed |
| 19.05.2026 | Notification of the survey |