WellplannerNorwegian shelf well data

Fields / Ivar Aasen / 16/1-D-11

16/1-D-11

Development, productionPluggedOil

Drilled by Det norske oljeselskap ASA with Maersk Interceptor in Ivar Aasen, 12.09.2015 to 29.09.2015 (17 days), to 4 294,0 m.

Water depth112,7 m
Total depth4 294,0 m MD
Vertical depth2 424,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table58,0 m
Formation at total depth-
RigMaersk Interceptor
Spud12.09.2015
Completed29.09.2015
OperatorDet norske oljeselskap ASA
Position58,9223 N, 2,1981 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-
Ivar Aasen gradient39,1 °C/km
Estimated at total depth from the gradient92 °C

The gradient is the median of 6 released wells in Ivar Aasen with a reported bottom-hole temperature, counted from 4 °C at the sea floor.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
16/1-D-11 A same well0,05 090,0--2015
16/1-U-70,01 530,0--2012
16/1-D-120,06 353,0--2017
16/1-D-12 AY10,06 317,0--2026
16/1-D-12 AY20,06 239,0--2026
16/1-D-15 Y10,05 035,0--2019
16/1-D-15 Y20,04 810,0--2019
16/1-D-15 Y30,04 810,0--2019

Casing and formation tests

No casing programme is reported for this wellbore.

Show on the mapOpen on FactPages ↗