Fields / 2/11-12 A
2/11-12 A
Exploration, wildcatPlugged and abandonedDry
Drilled by Aker BP ASA with Maersk Interceptor, 13.02.2019 to 07.03.2019 (22 days), to 3 427,0 m in the Zechstein Group.
Water depth70,5 m
Total depth3 427,0 m MD
Vertical depth3 245,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table55,0 m
Formation at total depthZechstein Group
RigMaersk Interceptor
Spud13.02.2019
Completed07.03.2019
OperatorAker BP ASA
Position56,1697 N, 3,4368 E
Formations
24 tops reported, measured depth in metres.
Temperature
| Reported at total depth | - |
The wellbore is not in a field, so no field gradient applies.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
| Wellbore | km | Total depth, m | BHT | Mud max, g/cm³ | Year |
|---|---|---|---|---|---|
| 2/11-12 S same well | 0,0 | 2 956,0 | - | 1,75 | 2019 |
| 2/11-5 | 0,4 | 2 945,0 | 106 °C | 1,80 | 1979 |
| 2/11-2 | 1,5 | 2 806,0 | 67 °C | 1,80 | 1974 |
| 2/11-A-1 | 1,6 | 4 723,0 | - | - | 1991 |
| 2/11-A-1 A | 1,6 | 4 137,0 | - | - | 1991 |
| 2/11-A-1 B | 1,6 | 3 823,0 | - | - | 1994 |
| 2/11-A-8 | 1,6 | 3 712,0 | - | - | 1995 |
| 2/11-A-8 A | 1,6 | 4 611,0 | - | - | 1995 |
Casing and formation tests
The casing programme as reported, shallowest first. The test is the leak-off (LOT) or formation integrity (FIT) result as an equivalent mud density.
| String | Casing | Shoe, m | Hole | Hole depth, m | Test, g/cm³ |
|---|---|---|---|---|---|
| Conductor | 20" | 535,8 | 26" | 541,0 | 1,63 LOT |
| Pilot hole | - | 540,0 | 9 7/8" | 540,0 | - |
| Intermediate | 13 3/8" | 1 426,4 | 16" | 1 435,0 | 1,95 LOT |
| Intermediate | 9 7/8" | 3 082,8 | 12 1/4" | 3 090,0 | 1,98 FIT |
| Open hole | - | 3 427,0 | 8 1/2" | 3 427,0 | - |
Mud weight
13 measurements, one dot each, 1,00 to 1,79 g/cm³ against measured depth, rheguard prime, sea water, warp.