2/4-FE-2
Development, productionClosed
Drilled by Aker BP ASA with Noble Integrator in Fenris, 12.10.2024 to 17.03.2025 (156 days), to 5 645,0 m.
Water depth68,3 m
Total depth5 645,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table63,9 m
Formation at total depth-
RigNoble Integrator
Spud12.10.2024
Completed17.03.2025
OperatorAker BP ASA
Position56,7000 N, 3,1190 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
| Fenris gradient | 34,9 °C/km |
| Estimated at total depth from the gradient | 196 °C |
The gradient is the median of 3 released wells in Fenris with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
Casing and formation tests
No casing programme is reported for this wellbore.