Drilled by Esso Exploration and Production Norway A/S with Saipem Ii in Frigg, 05.05.1973 to 18.07.1973 (74 days), to 2 917,0 m in the Hardråde Formation.
Water depth105,2 m
Total depth2 917,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table14,0 m
Formation at total depthHardråde Formation
RigSaipem Ii
Spud05.05.1973
Completed18.07.1973
OperatorEsso Exploration and Production Norway A/S
Position60,0057 N, 2,0687 E
Formations
21 tops reported, measured depth in metres.
Temperature
Reported at total depth
-
Frigg gradient
23,0 °C/km
Estimated at total depth from the gradient
68 °C
The gradient is the median of 7 released wells in Frigg with a reported bottom-hole temperature, counted from 4 °C at the sea floor. The vertical depth is not reported, so the measured depth is used and the estimate errs high.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.